Skip to content
All CMMC practices
CMMC · Rev 2.13L2PE · Physical Protection

PE.L2-3.10.4

Physical Access Logs [CUI Data]

Requirement

Maintain audit logs of physical access.

Assessment objectives

An assessor checks each lettered objective separately. The letters in brackets elsewhere on this page, such as [a] or [b,c], refer to these.

Determine if:

  1. aaudit logs of physical access are maintained.

From the CMMC Level 2 Assessment Guide v2.13 · publisher approved 2026-10-31.

How to implement

Keep a record of who enters your facility and its CUI areas, both employees and visitors, and retain those records for a period you define and follow. A paper sign-in sheet for visitors plus badge-reader logs (or a key and entry log) for employees is the usual way for small contractors, as long as the records are complete, protected and kept for the full retention period.

The minimum for a small organization · Expert CMMC's reading, not official text

Keep records of who enters the facility and the areas where CUI systems are, employees and visitors alike [a]: for example a visitor sign-in log at each entrance, and badge-reader entry logs or a sign-in sheet for staff. Decide how long the logs are kept and keep them where they cannot be lost or changed.

Required outcome: what the requirement or its objectives call for. Recommended way: one common way to get there. Going further: worth doing, more than this practice asks.

  1. 1
    Required outcomeProcessRecord who enters the facility and the areas where CUI systems are, employees and visitors alike, on paper or electronically, and keep the records for the period you define.[a]

    You can tell it worked when visitor and entry logs exist for the whole retention period (or since logging began, if that is shorter), kept where they cannot be lost or changed.

  2. 2
    Recommended wayPolicyDefine in the physical security policy which entry points and areas are logged (main entrance, CUI areas, server room), what each log records (name, organization, host, date, time in and out), where logs are stored and the retention period (for example one year, or longer if a contract requires it).[a]
  3. 3
    Recommended wayProcessLog visitors at every entry: a sign-in book or visitor-management system at reception, signed in and out, with the escort named. Do not allow side-door entry for visitors.[a]
  4. 4
    Recommended wayTechnicalLog authorized personnel: badge readers on entrances and controlled areas record each entry once logging is turned on and kept (check the controller's retention setting and that every reader feeds the log); without badge readers, use a sign-in log for the server room and CUI storage areas.[a]
  5. 5
    Recommended wayTechnicalProtect and retain logs: store paper logs in a locked cabinet; set the access-control system's log retention to at least your defined period (export periodically if the system keeps less); restrict who can edit or delete logs.[a]
  6. 6
    Recommended wayProcessReview logs monthly or after incidents for missing sign-outs, after-hours entries or access by people no longer authorized, and record the review.[a]

Evidence to collect

Artifacts that show the practice is implemented and operating. Tags show which assessment objectives each one supports.

A process you started recently is shown honestly by its dated procedure, the first record it produced and the date it began. No evidence row needs more history than the process has existed, and the review periods shown are suggestions unless a guide page or regulation is named beside them.

Physical access logging policy with retention period[a]

Also supports 5 other practices: keep it once

Log retention setting[a]

The detail for 5 evidence items: how to produce each, how fresh it must be, what it must include and what it does not show.

Free with an account. Create a free account or sign in.

How assessors check

What an assessor examines, asks and tests: 3 notes.

Free with an account. Create a free account or sign in.

Tools and products

Named options a contractor can adopt, with an honest cost tier. The industry standard is listed even when it is expensive, alongside what is free and acceptable for a very small shop.

Paper sign-in sheets in a locked cabinetVisitor and access loggingFree
UniFi Access / KisiBadge access loggingPaid
Brivo or Verkada access controlEnterprise access loggingEnterprise pricing
Envoy visitor managementVisitor loggingPaid

7 dated vendor facts and notes on 4 products for this practice: what each assumes, what it does not cover and what stays yours.

Free with an account. Create a free account or sign in.

Editorial mentions, not endorsements. Pricing and tiers change; confirm with the vendor and check FedRAMP or GCC High availability where CUI is involved.

Common pitfalls

  • Access-control system keeps only 30 days of events while the policy says one year.
  • Visitor sheets with no sign-out times or missing escorts.
  • Logs kept only at the building lobby by the landlord, which you cannot retrieve.
  • Logging the front door but not the server room or CUI storage area.

Platform notes

  • Microsoft 365 (GCC / GCC High)
  • Google Workspace
  • On-premises or MSP-managed

Notes for 3 platforms.

Free with an account. Create a free account or sign in.

Related practices: PE.L1-b.1.ix, PE.L2-3.10.3, PE.L2-3.10.5, AU.L2-3.3.1

Editorial implementation guidance published November 14, 2026. It is not part of the official requirement and does not replace the assessment guide.

The NIST requirements this practice is built on, what NIST made of each in the newer edition, and the SP 800-53 controls behind them, each from an official NIST or DoD table. Open any one to read it and see every CMMC practice it supports.

NIST SP 800-171 Rev 2

3.10.4

SP 800-171 Rev 3

03.10.0703.10.04 withdrawn; incorporated into

SP 800-53 Rev 4

PE-3

SP 800-53 Rev 5

PE-3DSPE-5S
How these were reached
  • PE-3 · Physical Access Control
    • D SP 800-171 Rev 2 Appendix D → SP 800-53 Rev 4 control → NIST's Rev 4 → Rev 5 comparison · via 800-53 Rev 4 PE-3 → 800-53 Rev 5 PE-3
    • S source control of the SP 800-171 Rev 3 or SP 800-172 Rev 3 requirement (NIST OSCAL) · via 800-171 Rev 3 03.10.07 → 800-53 Rev 5 PE-3NIST: 03.10.07 also: 3.10.3, 3.10.5 incorporated into
  • PE-5 · Access Control for Output Devices
    • S source control of the SP 800-171 Rev 3 or SP 800-172 Rev 3 requirement (NIST OSCAL) · via 800-171 Rev 3 03.10.07 → 800-53 Rev 5 PE-5NIST: 03.10.07 also: 3.10.3, 3.10.5 incorporated into

Rev 5 paths: D SP 800-171 Rev 2 Appendix D → SP 800-53 Rev 4 control → NIST's Rev 4 → Rev 5 comparison; S source control of the SP 800-171 Rev 3 or SP 800-172 Rev 3 requirement (NIST OSCAL); C SP 800-172 (Feb 2021) Appendix C. NIST also names this Rev 3 requirement as the successor of other withdrawn requirements: open “How these were reached” under the Rev 5 controls for which, in NIST's words.

Where each link comes from (7 links from 5 official documents)

32 CFR Part 170 Office of the Federal Register / GPO

  • PE.L2-3.10.4 → 3.10.4“Level 2 security requirement”32 CFR 170.14(c)(1) numbering (REQ is the NIST SP 800-171 R2 requirement number) and 170.14(c)(3)

NIST SP 800-171 Rev 2 → Rev 3 change analysis NIST

  • 3.10.4 → 03.10.04“Withdrawn”sheet "Change Analysis 800-171 R2-R3" row 85

NIST SP 800-171 Rev 3 (OSCAL) NIST

  • 03.10.04 → 03.10.07“Incorporated into”control 03.10.04 link rel=incorporated_into
  • 03.10.07 → PE-3“Source control”control 03.10.07 link rel=reference (PE-03)
  • 03.10.07 → PE-5“Source control”control 03.10.07 link rel=reference (PE-05)

NIST SP 800-171 Rev 2 NIST

  • 3.10.4 → PE-3“Appendix D mapping”p.90 Table D-10

NIST SP 800-53 Rev 4 → Rev 5 comparison NIST

  • PE-3 → PE-3“Changes parameter Changes discussion”sheet "Rev4 Rev5 Compared" row 567

Further discussion

Make sure you have a record of who accesses your facility (e.g., office, plant, factory). You can do this in writing by having employees and visitors sign in and sign out or by electronic means such as badge readers. Whatever means you use, you need to retain the access records for the time period that your company has defined. Example You and your coworkers like to have friends and family join you for lunch at the office on Fridays. Your small company has just signed a contract with the DoD, however, and you now need to document who enters and leaves your facility. You work with the reception staff to ensure that all non-employees sign in at the reception area and sign out when they leave [a]. You retain those paper sign-in sheets in a locked filing cabinet for one year. Employees receive badges or key cards that enable tracking and logging access to company facilities. Potential Assessment Considerations • Are logs of physical access to sensitive areas (both authorized access and visitor access) maintained per retention requirements [a]? • Are visitor access records retained for as long as required [a]?

Practice guide notes

Implementation guidance

Editorial examples to help you plan. Adapt them to your environment; the official requirement and objectives remain authoritative.

In plain language

Maintain audit logs of physical access.

Implementation example

Example from the source assessment guide (not a mandatory implementation): You and your cow orkers like to have friends and family join you for lunch at the office on Fridays. Your small company has just signed a contract with the DoD, however, and you now need to document who enters and leaves your facility. You work with the reception staff to ensure that all non-employees sign in at the reception area and sign out when they leave [a]. You retain those paper sign- in sheets in a locked filing cabinet for one year. Employees receive badges or key cards that enable tracking and logging access to company facilities.

Evidence examples

Examples suggested by the source guide (not an exhaustive or mandatory checklist): Physical and environmental protection policy; procedures addressing physical access control; system security plan; physical access control logs or records; inventory records of physical access control devices; system entry and exit points; records of key and lock combina tion changes; storage locations for physical access control devices; physical access control devices; list of security safeguards controlling access to designated publicly accessible areas within facility; other relevant documents or records

Common mistakes

Having access controls without records sufficient to review physical entry.

Track this in a workspace

The compliance workspace tracks each objective, its evidence and the tasks to close gaps. It is open to invited contractors while in pilot: request access below.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

Source: DoD CIO · https://dodcio.defense.gov/CMMC/